5.4 Insert Instrument Valves or Manifold
5.4.1 Valves
If the Verabar does not have a valve head, install
instrument valves using proper thread sealant. Be sure
instrument shut-off valves are installed and shut prior to
repressurizing the pipe.
5.4.2 Manifold
If the Verabar has a direct or integral manifold, be sure
the high and low pressure block valves are shut off prior
to repressurizing the pipe.
The Verabar is now properly installed (Figure 5).
Figure 5. Installed V100
Periodic Maintenance
The assembly should be periodically checked. Verify
that no leaks are present.
6315 Monarch Park Place Niwot, CO 80503 USA Phone: (303) 652-8550 IO -100 VWI-CS-020 REV B (6/08)